Why damage shows up late

A tree doesn't fall over the week the excavator arrives. That's what makes construction harm hard to see. When heavy equipment drives over the ground or stacks material on it, the soil gets compacted, and compaction cuts off air and water to the roots. Clemson's home and garden extension notes that the damage occurs slowly and may not show for several years.

So the tree can look fine at final inspection and start thinning out in the crown long after the crew has gone. By then it's hard to connect cause and effect, and harder to fix. The cheapest time to protect a tree is before the first dig.

Protect the root zone

Roots reach well past the trunk. The ground under the outer edge of the branches is called the dripline, and the usual advice is to keep people and machines out of that area entirely. Clemson recommends barriers placed beyond the dripline of a tree or a group of trees.

Sturdy fencing is the simple answer. The fence should go up before any equipment arrives and stay up until the work is done. Make sure the builder and every subcontractor know that nothing gets parked, stacked or dumped inside it.

Some sites don't have the room for a full fence. In that case Clemson suggests spreading several inches of wood chips over the root zone area, or bridging the root area with steel plates. Both spread the load so the soil underneath isn't crushed as badly. They're a fallback. A proper fence does more.

Grade changes

Changing the ground level around a tree can hurt it, because the roots depend on the soil they're growing in staying much as it is.

Taking soil away

Taking soil away is the milder case. Clemson says removing 1 to 2 inches of soil normally won't affect a tree's growth. Clemson gives no safe figure for anything deeper. It advises retaining walls or terraces so you don't strip away soil from the area of greatest root growth, so ask before you cut a slope near a tree.

Adding fill

Piling soil on top of roots can smother them. What's needed depends on how deep the fill is. Clemson's main method is an aeration system of gravel and buried perforated pipe or clay tile, laid before the fill. For fill of 30 inches or less it describes a simpler gravel layer with no pipe.

You don't need to design that yourself. What matters is that a plan exists before anyone hauls in a single load. Fill is hard to take back out once it's down, and a tree under it can decline for years without anyone connecting the two.

Trenching and utilities

Utility trenches cut roots, and big roots hold the tree up and feed it. Clemson points out that underground utilities don't have to run in a straight line from the street to the house, so the route can bend around a tree. Where roots can't be avoided, tunneling beneath them does less harm than cutting through.

Foundations matter too. A continuous footing needs a continuous trench. Clemson suggests posts and pillars in place of footers and walls, which means fewer and smaller holes near the roots. Raise this with your architect while the plans are still on paper, since it's much cheaper to change a drawing than a foundation.

Permits and plans

Many cities protect certain trees, and some ask for real paperwork before anyone builds near them. Menlo Park, California, is one example. Its heritage tree permit for development projects asks for a tree inventory and appraisal values, construction plans, and alternative designs that would preserve the tree, with their costs. Every application also needs an arborist report from a consulting arborist the city has approved.

Rules differ from one city to the next, so check with your city's planning or public works office before you finalize a design, since a permit that comes late can hold up the whole job. If you're not sure what your city will ask for, tell us when you send your request. See our page on tree protection plans for what we write.

What a protection plan costs

A protection plan is a written document, signed by a consulting arborist, that says which trees stay, how far the protection zone reaches, where fences go and what work is allowed inside it. Builders can follow it, and a city can review it.

Prices vary. One tree care company, BridgeWood, lists a flat fee of $500 to $800 for a residential preservation plan and $800 to $1,500 for a commercial one. It also lists hourly rates of $150 to $250 for a site visit and consultation, and $200 to $300 for monitoring during construction. It says these are averages that change with the size and complexity of the job.

Ours is $1,250 for a residential lot, and it includes a plan sheet your builder can pin up on site. Commercial sites and multiple lots start at $2,500 and are quoted after a call. That's above BridgeWood's range for a residential plan. Ours is signed by the named consulting arborist who wrote it, and we don't do tree work, so nothing in the plan is there to win you a job. Full prices are on our pricing page.

A plan can't promise that a tree will survive construction. It can lower the risk and show that you took reasonable steps.

Sources